Full Case Caption
CAMPBELL v. DISTRICT OF COLUMBIA
Official & Parallel Citations
117 U.S. 615 · 29 L. Ed. 1007 · 6 S. Ct. 922
Court & Volume
Supreme Court of the United States · 117 U.S.

Syllabus & Case Posture

CAMPBELL v. DISTRICT OF COLUMBIA.

ERROR TO THE SUPREME COURT OE THE DISTRICT OF COLUMBIA

Argued April 1, 2, 1886.

Decided April 12, 1886.

O & H, partners, contracted with the District of "Columbia to put down a water main. They notified the agent of the District that they authorized C to perform the work and receive the money, and the agent accepted the arrangement. C performed the work, and receipted from time to time for payments on the contract. On a suit in his own name for extra work: Held, Th»t he wa-s bound by the terms of the contract in that respect, and by receipts given in accordance therewith.

Assumpsit to recover for work and' labor done and materials furnished on the construction of a water main in Georgetown in the District of Columbia.. The record showed that in July, 1870, the District contracted with O’Hare, Himber & Co. for the construction of the main, by a written contract which provided, among other things, that “No claims for extra work shall be made unless the same shall be done in pursuance of a written order from the engineer.” Soon after commencement of the work, a member of ,the firm of O’Hare, Himber & Co., by their authority, addressed the following letter to the superintendent in charge of the construction oh the part of the District:

Opinion of the Court — Ms. Chief Justice "Waite

Primary Opinion

Ms. Chief Justice "Waite

delivered the opinion of the court.

This judgment is affirmed. There was no evidence whatever in the case tending to prove that'.the work was done by Campbell otherwise than under the contract of O’Hare, Him-ber & Co. He took the place of that firm in the contract so far as the,work he undertook to do was concerned. Davenport, one-*of its members, authorized him. to do the work and receive the pay upon vouchers, which he, Davenport, agreed to sign. It was upon this, authority that Campbell entered upon the work, with the permission of the chief engineer in charge.- In this way he became bound, by-the terms of, the contract. Under these circumstances, his acceptance of the allowance rhade by the chief engineer for-all his present claims for. extra work, as “in full settlement of the above stated claim,” operated as a complete discharge of the District from all further liability to him on that account. - The provision in the act of the legislative assembly of the District, “ that this • receipt shall not debar the above named persons from any right they may have in any court,” clearly applies only to the claim, of Robert Strong & Co. As to all others, named in the act, “the receipt was to be in full of \ all claims on account of the-said work,” •

• Affirmed.