United States v. Shrewsbury

90 U.S. 508 1874-10 3,568 Words
Full Case Caption
United States v. Shrewsbury
Official & Parallel Citations
23 Wall. 508 · 90 U.S. 508 · 23 L. Ed. 78
Court & Volume
Supreme Court of the United States · 90 U.S.

Syllabus & Case Posture

United States v. Shrewsbury.

Where, under a contract entered into between the government and a transporter of military stores, in the wilds of the West, it was provided that a board of survey, composed of military officers, should on the arrival of the stores at their place of delivery, examine the quantity and condition of the stores transported, and “in case of loss, deficiency, or damage, investigate the facts and report the apparent causes, assess the amount of loss and injury, and state whether it was attributable to neglect or want of care on the part of the contractor or to causes beyond his control,” a copy of which, said the contract, “ shall be furnished to the contractor, shall be attached to the bill of lading, and shall conclude the payments to be made” — Held, that a report which did not report investigation of facts and the apparent causes, nor state whether the loss was attributable to neglect or the want of care on the part of the contractor or to causes beyond his control, but which merely on its face found the deficiency and charged it accordingly would be supported; the contractor not having at the time objected either as to the form or the substance of the report, when it was made; and objecting only when he came and got his money; when witnesses were scattered and gone, and most of them difficult if not impossible to be found; and then notifying to the quartermaster nothing more definite than that he, the contractor, would claim a readjustment and full damages.

Appeal from the Court of Claims.

The case as found by the Court of Claims was thus:

On the 27th of March, 1865, "W. S. Shrewsbury entered into a contract with the United States to transport army stores from Fort Leavenworth, Kansas, and other forts there and in Missouri, to Fort Lyon and other forts in the Territories of Colorado and New Mexico.

The contract contained a clause thus:

Opinion of the Court — Mr. Justice S WAYNE

Primary Opinion

Mr. Justice S WAYNE

delivered the opinion of the court.

The counsel for the appellee maintains that the Court of Claims in holding as it did for nought the findings and recommendations of the board was right, because the agreement was, that in case of deficiency, the board should “investigate the facts and report the apparent cause, and assess the amount of loss or injury, and state whether it was attributable to neglect or want of care on the part of the contractor, or to causes beyond his control,” and that their proceedings failed to carry out the intent and terms of the contract in these particulars. This is too narrow and technical a view of the subject. The provision of the contract touching the board was important to the government. The points of delivery were in the wilds of the West. If there was any failure by the contractor, the time and place of delivery -were the time and place to ascertain the facts, and to put the evidence in an effectual shape. Afterwards it might be impossible for the government to procure the proofs, and if it were done, the expense might greatly exceed the amount of the items in dispute. At the delivery, the bill of lading spoke for itself. The teamsters and guards who accompanied the train were present, and could readily be examined. It is said by the Court of Claims, in their conclusions of law, that the board failed to make the requisite investigations of the facts. To do this was one of the most important duties devolved upon them. It is to be presumed they discharged it. They did not say, in terms, that they had done so, but they reported conclusions carrying with them the strongest implication that what was recommended rested on a basis of ascertained facts. The board, as honest men, could not have announced such results without the proper previous examination. The means were at hand, and the work was easy. A formal and technical instrument was not to be expected from military men acting under such circumstances. We think the reports were sufficient, and that they conform in every substantial particular to the requirements of the contract.

It does not appear that'the contractor objected either as to form or substance when the reports were made, nor that he disclosed any objection subsequently until the time of payment. Nor did his objections then assume a definite shape. He notified the quartermaster that he should claim “a readjustment and full payment.” The reasons and grounds of the claim were not stated. The payments were made at a distant point and after the lapse of several months. The witnesses were then scattered and gone. Most of them doubtless were difficult if not impossible to be found. As the contractor was silent when he should have spoken, he cannot be permitted to speak at the later period, in the altered condition of things, which then existed, as regards the other party. He must be held to have waived any exception which he might have taken at the proper time, and to have been, when the payments were made, finally concluded.

Judgment reversed, and the case remanded, with directions

To DISMISS THE PETITION.

Mr. Justice FIELD dissented.